The scope of work will provide
a major new pumping station which will collect flow from areas located south of the 6th Ring Road, Fahaheel Interceptor, Fahaheel coastal catchment area and then convey the flow through three pressure mains of diameter 1400 from Egaila Pumping Station to Riqqa waste water treatment plant in length of 5.220 kms.
Within the project area, a gravity line along the main Fahaheel coastal road will be constructed in length of 2 km in diameter of 2250.
Also a gravity line with 1000mm diameter will be constructed collecting flow from transit chamber from south of Hadeya till it reaches A-15 Pumping Station and then reaches Egaila Pumping Station.
Also treated effluent line in 300 mm diameter will be constructed from Riqqa waste water treatment plant till it reaches Egaila Pumping Stat-
Project Details
Location:
Egaila.
Client:
Ministry of Public Works, Sanitary Engineering.
Services Performed:
Full Design & Construction Supervision.
Cost:
KD. 28.70 million.
Completion:
2009.
-ion to be used for landscaping around the site. The area of Egaila Pumping Station is 100m x 150m in depth reaching 48m.The Egaila Pumping Station is designed to take 362,880 m3 flow by year 2035.
After completion and commissioning of the new year system and the pump station, the existing pump sta-tion A-14 and A-15 will be demolished. Also along the Fahaheel expressway existing lifting stations S-16, S-17, S-18, S-19 and S-20 will be abandoned.
This project is being undertaken in association with Parsons Engineering Science (USA).